COLDWATER – The Coldwater Board of Public Utilities purchased 37 transformers in order to fill the need for local power.
Coldwater’s Electric Superintendent John Springhall explained with supply chain shortages throughout the nation new construction builds are being impacted.
Springhall noted the apartments on Willowbrook Lane waited a year for the arrival of their transformers.
Transformers previously took around 10 weeks to arrive but are now taking 50-60 weeks or longer.
The purchase which cost the Coldwater Board of Utilities $109,249 was made to ensure all local needs were met in any future projects.
(11-07-2025) Former Steuben Co Detective Not Guilty of Official Misconduct and Criminal Mischief
(11-06-2025) Hoosier Veterans Get Additional Help During SNAP Delays
(11-06-2025) SNAP Benefits Delayed Amid Recalculations
(11-06-2025) Indiana Attorney Gen Asks Trump To Deploy Nat Guard to Indy
(11-06-2025) Former Steuben Co Detective's Trial Begins
(11-05-2025) Angola Water and Wastewater Rates Likely Going Up - But Not Immediately
(11-05-2025) Traffic Roundabout To Be Built at CR 100N & CR 200W in Angola
(11-05-2025) Steuben Co Commissioners Want to Talk About Casino Relocation
(11-04-2025) Habitat For Humanity of NE Indiana Ends Efforts After 31 Years
(11-04-2025) Shipshewana Town Marshal Under Investigation
(11-04-2025) Wildwood Homeowners Ask Steuben Co Commission for Help with Messy Neighbors
(11-04-2025) Man Gets Car Stuck on Utility Pole - Now Faces Deportation
(11-04-2025) IN Lawmakers Opt for Early Return In Lieu of Special Session
(11-03-2025) Irsay Family to Auction Off Huge Collection For Charity
(11-03-2025) Butler Teen Killed By Train
(11-03-2025) Angola Marching Hornets Headed to State - Will Host Local Performance
(11-03-2025) Trine Women's Cross Country Team Wins First Ever Conference Title
(11-01-2025) Corporate Toboggan Speed Challenge at Pokagon
(10-31-2025) FW Man Seriously Injured in DeKalb Car Accident
(10-30-2025) List of Townwide Trick-or-Treating Schedules